/5 1 GATE Architecture & Govt. Jobs Prepare for GATE Architecture & Planning (AR) 2027-28 with free online quizzes and mock tests by KP GATE Classes. Practice Architecture MCQs, PYQs, Planning, Structures, Building Materials, and Government Architecture Exam questions with instant answers and real exam-level practice. A Classroom of 12 m x 25 m x 4 m requires 3 air changes per hour. At an air velocity of 2 m/s, the necessary duct cross-section (in m²) is 1.00 0.75 1.5 0.50 Volume = 12×25×4 = 1200 m³. With 3 air changes/hour, required flow = 1200×3 = 3600 m³/hour. Convert to m³/s: 3600 / 3600 = 1.0 m³/s. With air velocity 2 m/s, required area = Q / V = 1.0 / 2 = 0.5 m². Which of the following parameters is essential to estimate the Envelope Performance Factor (EPF) of a building as per Energy Conservation Building Code (ЕСВС), 2011? Maximum and minimum monthly temperature Building occupancy duration Building type Maximum humidity The Envelope Performance Factor (EPF) assesses building envelope energy performance and accounts for internal heat gains and usage patterns. Building occupancy duration (operating hours) is essential because the envelope’s thermal performance interacts with HVAC operating schedules — longer occupancy increases conditioning hours and thus energy impact of envelope losses/gains. ECBC envelope compliance calculators use climate data together with building type and occupancy schedules to size glazing, insulation and shading. While temperature extremes and building type matter, EPF calculations explicitly require occupancy duration to estimate annual heating/cooling loads and hence the envelope’s relative performance. The best location for laying the main sewer line on a flat land is under the central verge under the open space along sidewalk under the side walk Under the road Placing the main sewer under the road is standard practice: roads provide continuous linear corridors with public right-of-way, easier access for inspection and maintenance, and reduced need for private land acquisition. Road trenches avoid disturbance of buildings, avoid compromising private compound space, and permit alignment with other utilities in planned utility corridors. Sidewalks or central verges may be used for smaller drains, but the main trunk sewer benefits from road alignment to maintain required slope, accessibility for repair, and integration with manholes and laterals. This minimizes conflicts with private property and streamlines construction and operation. A sanitary landfill is provided with High Density Polyethylene (HDPE) lining along the ground surface. This is provided primarily to prevent bleaching A sanitary landfill is provided with High Density Polyethylene (HDPE) lining along the ground surface. This is provided primarily to prevent plant growth rodents A High Density Polyethylene (HDPE) liner is installed at the base of modern sanitary landfills to prevent leachate (contaminated liquid) percolating into the ground and contaminating groundwater and soil. The impermeable HDPE membrane, often combined with compacted clay and geotextiles, provides containment. It does not primarily target rodents, plant growth or bleaching. Proper liner systems reduce pollution risk, allow controlled leachate collection and treatment and are central to engineered sanitary landfill design standards aimed at protecting public health and the environment. The purchase price of BHK flat rises 10 percent. The demand for such flats is observed to decrease by 8 percent. The given elasticity of the housing demand for 2010-11 (flat is rounded off to one decimal place) is 0.8 80 0.08 8 Price elasticity of demand = (% change in quantity demanded) / (% change in price). Here demand falls by 8% when price rises by 10% → elasticity = −8% / +10% = −0.8. The magnitude 0.8 (rounded to one decimal) indicates inelastic demand (|ε| &l < 1): buyers reduce quantity less than proportionally to the price increase. For housing, inelastic responses are common over short periods due to transaction costs and housing being a necessity. The negative sign denotes the inverse relation; exam options typically list magnitudes, so 0.8 is the correct numeric choice. Congratulations! You’ve completed the test. Fill out the form to view your result. Your score isThe average score is 40% 0% Restart quiz
GATE Architecture & Govt. Jobs
Prepare for GATE Architecture & Planning (AR) 2027-28 with free online quizzes and mock tests by KP GATE Classes. Practice Architecture MCQs, PYQs, Planning, Structures, Building Materials, and Government Architecture Exam questions with instant answers and real exam-level practice.
A Classroom of 12 m x 25 m x 4 m requires 3 air changes per hour. At an
air velocity of 2 m/s, the necessary duct cross-section (in m²) is
Volume = 12×25×4 = 1200 m³. With 3 air changes/hour, required flow = 1200×3 = 3600 m³/hour. Convert to m³/s: 3600 / 3600 = 1.0 m³/s. With air velocity 2 m/s, required area = Q / V = 1.0 / 2 = 0.5 m².
Which of the following parameters is essential to estimate the Envelope Performance Factor (EPF) of a building as per Energy Conservation Building Code (ЕСВС), 2011?
The Envelope Performance Factor (EPF) assesses building envelope energy performance and accounts for internal heat gains and usage patterns. Building occupancy duration (operating hours) is essential because the envelope’s thermal performance interacts with HVAC operating schedules — longer occupancy increases conditioning hours and thus energy impact of envelope losses/gains. ECBC envelope compliance calculators use climate data together with building type and occupancy schedules to size glazing, insulation and shading. While temperature extremes and building type matter, EPF calculations explicitly require occupancy duration to estimate annual heating/cooling loads and hence the envelope’s relative performance.
The best location for laying the main sewer line on a flat land is
Placing the main sewer under the road is standard practice: roads provide continuous linear corridors with public right-of-way, easier access for inspection and maintenance, and reduced need for private land acquisition. Road trenches avoid disturbance of buildings, avoid compromising private compound space, and permit alignment with other utilities in planned utility corridors. Sidewalks or central verges may be used for smaller drains, but the main trunk sewer benefits from road alignment to maintain required slope, accessibility for repair, and integration with manholes and laterals. This minimizes conflicts with private property and streamlines construction and operation.
A sanitary landfill is provided with High Density Polyethylene (HDPE) lining along the ground surface. This is provided primarily to prevent
A High Density Polyethylene (HDPE) liner is installed at the base of modern sanitary landfills to prevent leachate (contaminated liquid) percolating into the ground and contaminating groundwater and soil. The impermeable HDPE membrane, often combined with compacted clay and geotextiles, provides containment. It does not primarily target rodents, plant growth or bleaching. Proper liner systems reduce pollution risk, allow controlled leachate collection and treatment and are central to engineered sanitary landfill design standards aimed at protecting public health and the environment.
The purchase price of BHK flat rises 10 percent. The demand for such flats is observed to decrease by 8 percent. The given elasticity of the housing demand for 2010-11 (flat is rounded off to one decimal place) is
Price elasticity of demand = (% change in quantity demanded) / (% change in price). Here demand falls by 8% when price rises by 10% → elasticity = −8% / +10% = −0.8. The magnitude 0.8 (rounded to one decimal) indicates inelastic demand (|ε| &l < 1): buyers reduce quantity less than proportionally to the price increase. For housing, inelastic responses are common over short periods due to transaction costs and housing being a necessity. The negative sign denotes the inverse relation; exam options typically list magnitudes, so 0.8 is the correct numeric choice.
Congratulations! You’ve completed the test. Fill out the form to view your result.
Your score is
The average score is 40%