/5 2 GATE Architecture & Govt. Jobs Prepare for GATE Architecture & Planning (AR) 2027-28 with free online quizzes and mock tests by KP GATE Classes. Practice Architecture MCQs, PYQs, Planning, Structures, Building Materials, and Government Architecture Exam questions with instant answers and real exam-level practice. “Risk” usually _____ as the project progresses Become negligible Remains same Increases Reduces As a project progresses, more information becomes available about the project and its potential risks. This allows the project team to identify and mitigate risks, leading to a decrease in overall risk Which projects need RERA registration? All of the above Residential & Commercial Land under development more than 500 SQFT or 8 units Plotted development Residential and Commercial: RERA applies to both residential and commercial projects, meaning apartments, buildings, and plots intended for sale or lease under this regulation. Plotted development: Even if a project is just selling plots of land, it needs to be registered under RERA if the total land area developed exceeds 500 square meters. Land under development more than 500 SQFT or 8 units: This is a key criterion for RERA registration, regardless of the project type. If a project involves developing more than 500 square meters of land or constructing more than eight apartments, it must be registered with RERA. The PERT in project management means program evaluation and _____ technique. Reconsideration Reconciliation Review Resource PERT stands for "Program Evaluation and Review Technique". It's a project management tool that helps visualize and manage complex projects by assessing each task and its relationship to others within the timeline. "Review" aligns with the concept of evaluating and assessing the progress of a project throughout its development. Which one of the following is not correct? Part IX-A of the Constitution of India pertaining to the Municipalities provides For setting up a separate Finance Commission for the Municipalities For setting up Committee for District Planning For setting up Committee for Metropolitan Planning That grants-in-aid be made to the Municipalities from the Consolidated Fund of the State For setting up a separate Finance Commission for the Municipalities Explanation While Part IX-A deals with Municipalities, it does not mandate the establishment of a separate Finance Commission specifically for them; instead, the existing State Finance Commission is responsible for reviewing the financial position of both Panchayats and Municipalities and making recommendations regarding grants-in-aid to them. To whom does the Chairperson of every Metropolitan Planning Committee forward the development plan, as recommended by such a Committee? The Finance Minister, Government of India The State Government The Planning Commission The Urban Development Minister, Government of India The Chairperson of a Metropolitan Planning Committee forwards the development plan to the State Government. According to the 74th Constitutional Amendment Act, Metropolitan Planning Committees are responsible for preparing development plans for metropolitan areas. These committees are required to forward the draft plan to the State Government for further action. Congratulations! You’ve completed the test. Fill out the form to view your result. Your score isThe average score is 50% 0% Restart quiz
GATE Architecture & Govt. Jobs
Prepare for GATE Architecture & Planning (AR) 2027-28 with free online quizzes and mock tests by KP GATE Classes. Practice Architecture MCQs, PYQs, Planning, Structures, Building Materials, and Government Architecture Exam questions with instant answers and real exam-level practice.
“Risk” usually _____ as the project progresses
As a project progresses, more information becomes available about the project and its potential risks. This allows the project team to identify and mitigate risks, leading to a decrease in overall risk
Which projects need RERA registration?
Residential and Commercial:
RERA applies to both residential and commercial projects, meaning apartments, buildings, and plots intended for sale or lease under this regulation.
Plotted development: Even if a project is just selling plots of land, it needs to be registered under RERA if the total land area developed exceeds 500 square meters.
Land under development more than 500 SQFT or 8 units: This is a key criterion for RERA registration, regardless of the project type. If a project involves developing more than 500 square meters of land or constructing more than eight apartments, it must be registered with RERA.
The PERT in project management means program evaluation and _____ technique.
PERT stands for "Program Evaluation and Review Technique". It's a project management tool that helps visualize and manage complex projects by assessing each task and its relationship to others within the timeline. "Review" aligns with the concept of evaluating and assessing the progress of a project throughout its development.
Which one of the following is not correct? Part IX-A of the Constitution of India pertaining to the Municipalities provides
For setting up a separate Finance Commission for the Municipalities Explanation While Part IX-A deals with Municipalities, it does not mandate the establishment of a separate Finance Commission specifically for them; instead, the existing State Finance Commission is responsible for reviewing the financial position of both Panchayats and Municipalities and making recommendations regarding grants-in-aid to them.
To whom does the Chairperson of every Metropolitan Planning Committee forward the development plan, as recommended by such a Committee?
The Chairperson of a Metropolitan Planning Committee forwards the development plan to the State Government. According to the 74th Constitutional Amendment Act, Metropolitan Planning Committees are responsible for preparing development plans for metropolitan areas. These committees are required to forward the draft plan to the State Government for further action.
Congratulations! You’ve completed the test. Fill out the form to view your result.
Your score is
The average score is 50%
Restart quiz